Marco Antonio Rocha has lived across from an empty lot on East Beyer Boulevard for close to three decades. When machinery finally showed up there in August 2024, he wasn't ready to celebrate. He'd seen this before: trucks, noise, neighbors taking photos, and then nothing the next day. This time was different. The lot is now Beyer Park, San Ysidro's first new public park in over 25 years, and its skatepark has been open and free to the public since at least July 2026.
The park sat on paper for longer than most of its future users have been alive. San Ysidro's 1974 community plan set aside the land. The 1990 plan repeated the request. So did the 2016 plan. Fifty-two years is a long time to wait for a place to skate.
What makes this moment worth writing down isn't just that one long-delayed park opened. It's that San Ysidro's community center also reopened this summer after a multimillion-dollar renovation, and a few miles north in National City, a bike path segment that's been stuck for over a decade finally has a construction contract on the calendar. Three separate waits, three separate funding fights, all clearing in roughly the same twelve months. That's not a coincidence worth glossing over. It's the actual mechanism by which underfunded corners of the county get their infrastructure, and understanding it explains why this stretch of San Diego Bay has felt frozen for years and suddenly doesn't.
Beyer Park sits on a 43-acre site, with the first 8 acres now built out. That finished phase includes a children's playground with a rock climbing wall, basketball courts, adult fitness equipment, walking paths, and the skate park where Rocha's grandkids and half the neighborhood have apparently already worn a line in the concrete. A dog park and ball fields have been part of the plan since the city first described the project, though the city's own phase breakdown doesn't specify exactly when those land. A second phase, still to come, adds multi-use turf fields, more picnic areas with shade structures, additional parking, and more trail.
The park's centerpiece isn't athletic. It's a public art installation called "Air Sanctuary," created by artists Ingram Ober and Marisol Rendón. A single ironwood tree grows inside a sculptural enclosure, meant to be watched as it changes with the seasons rather than admired once and forgotten. It's an odd thing to put at the center of a skatepark and a dog run, and that's probably the point.
The total project runs about $22.4 million, and no single check paid for it. A million came from the city's park impact fee fund in March 2024. Another $2.5 million came through a federal Community Development Block Grant. The largest piece, $8.5 million, came from California's Statewide Park Development and Community Revitalization Grant Program. Representative Juan Vargas helped secure $5 million from the Department of the Interior's Outdoor Recreation Legacy Partnership program plus another $3 million in federal community project funds for phase two. Councilmember Vivian Moreno, whose district includes San Ysidro, has said outright that city hall promised this park for over 30 years and past leadership never delivered.
"You're going to have people from all over playing soccer, playing softball, playing baseball," neighbor Alberto Perez told a local news crew during groundbreaking. "It was about time."
Perez has lived across the street for 38 years. He'll get to watch the second phase from his porch, too, whenever that funding stack finishes assembling itself.
While Beyer Park was under construction, the Col. Irving Salomon San Ysidro Community Activity Center was going through its own overhaul. It reopened on July 28, 2026, after a $5.8 million renovation that added a new multi-purpose sports court, an accessible playground, upgraded restrooms, and a resurfaced parking lot. Roughly $4 million of that came from a U.S. Department of Housing and Urban Development grant, with the rest pieced together from San Ysidro Urban Community funds, city capital outlay dollars, and park development impact fees.
Programming resumed within days of the ribbon-cutting. If you're trying to book the space or check class schedules, the center's direct line is 619-424-0472, or you can reach Parks and Recreation at 619-534-3377.
Two major public facilities in the same neighborhood, reopening or opening for the first time within weeks of each other, funded through almost entirely different channels. That's the pattern worth paying attention to.
The Bayshore Bikeway is a 24-mile loop that's supposed to let a cyclist ride the entire perimeter of San Diego Bay without leaving a dedicated path. Chula Vista got its segment built in 2012. A scenic stretch elsewhere on the loop was finished in 2015. A mile-long piece along Harbor Drive was completed in early 2018. National City's Segment 5, the piece that would actually connect the northern and southern halves of the loop through the city, sat unbuilt for years after everyone else's homework was done.
That changed with money, as these things do. SANDAG awarded National City a $5.7 million construction grant in early 2025. The Port of San Diego's board followed with a $2 million matching commitment that July, split between $600,000 from the Maritime Industrial Impact Fund and $1.4 million from the Port's grant reserves. By last fall, city engineers told National City's Rapid Safety Committee that the funding gap had finally closed and set a target to award the construction contract this September.
The finalized alignment runs down Harbor Drive, crosses the BNSF railroad tracks with new signal work coordinated through the California Public Utility Commission, ducks under a Caltrans off-ramp onto McKinley Avenue, and threads through Marina Way and a marsh area before tying into the existing path. It's not a clean line through empty space. Mitchell Beacham, secretary of the National City Depot Museum, raised concerns about losing parking used during museum events. Nineteenth Street will close to car traffic entirely and become pedestrian and bike only. Near Kimball Elementary, the design adds "always stop" controls at key intersections. These are the kinds of details that only show up once a project has actually cleared its funding and moved into real engineering, which is itself a sign of how far this one has come.
| Project | First promised | What finally closed the gap | Status as of September 2026 |
|---|---|---|---|
| Beyer Park | 1974 community plan | Stacked state park bond, federal CDBG, and Interior Dept. grants | Phase 1 open, including skatepark |
| Bayshore Bikeway Segment 5 | Part of SANDAG's original 24-mile loop plan | SANDAG grant plus Port of San Diego matching funds, 2025 | Construction contract targeted for this month |
A few blocks from where Segment 5 will eventually run, Pepper Park picked up its own upgrades in early 2026: a pirate-themed playground, a splash pad, and a toddler play area, with a hillside play area still in the rendering stage. Pepper Park sits inside National City's roughly 60-acre Marina District, which the Port of San Diego and the city have been reworking under something called the National City Balanced Plan. The California Coastal Commission certified that plan, and the Port's board formally accepted the certification on February 17, 2026. Part of the plan expands Pepper Park itself by about 2.5 acres, close to a 50 percent increase from its current 5.19 acres.
It would be tidy to say San Diego decided to invest in this stretch of the bay all at once. That's not what happened. Beyer Park cleared because a state park bond program, a federal block grant, and a congressional earmark all came through in overlapping years. The Activity Center cleared because HUD funding and local capital dollars aligned on their own separate timeline. The bikeway cleared because SANDAG and the Port matched grants a full year apart, and the alignment fight with the railroad and Caltrans took its own time to settle.
None of these funding sources talk to each other. They just happened to finish clearing their individual hurdles in the same rough window, which made 2026 feel like the year San Ysidro and National City caught up all at once.
It's also worth knowing that the same system doesn't always cooperate this cleanly. A few miles south, Imperial Beach has its own Bayshore Bikeway project, a flood-proofing effort for a stretch of the path near Bayside Elementary, and as of this past spring, its $15.7 million FEMA grant was sitting on a waitlist with no clear timeline. Same bikeway, same regional plan, completely different funding luck.
That's the actual takeaway if you live in this part of the county. Progress here doesn't arrive as one announcement. It arrives in pieces, on separate clocks, and some pieces wait decades while others move in eighteen months. Beyer Park and the bikeway both happened to clear in 2026. The bikeway resiliency project in Imperial Beach is still waiting its turn.
If you want to see any of this for yourself, Beyer Park's skate park is open now on East Beyer Boulevard, the Activity Center is back to regular programming, and Pepper Park's splash pad is already drawing families on warm afternoons. The bike path connecting it all is the one still worth watching this month.
For those of you thinking further down the road about what any of this means for property in San Ysidro, National City, or elsewhere across San Diego, The Foley Group has spent years tracking exactly this kind of neighborhood-level change. Let's Connect whenever you're ready to talk through what it means for you.